We would like to inform you that at the construction site of the Retail Park in Olsztyn, at 36 Sielska Street, the mullion and transom construction of the shop windows and their glazing is currently being installed. The installation of internal walls between units is also underway. Floors and internal installations are also being made in parts of the building.
At the same time, work is underway on the roofing, external installations, paved surfaces and the reconstruction of Sielska Street and the construction of a roundabout. In March, work is planned on laying some of the bituminous surfaces.
Work is also progressing gradually on the construction of the pedestrian and cycle path along Sielska Street.
The works related to the construction of the petrol station are progressing according to schedule, at the moment the building is already closed with walls, the structure of the shed is standing and works related to fuel technology are being performed.