PROGRESS OF CONSTRUCTION IN NOWE BABICE

20, 01, 2020

The installation of the showcases is still in progress and the first glazing elements have been installed. Laying of the hydrant system of building E began.

Work on buildings G and H is in progress on laying the roof layers.

In building H most of the terrazzo floors have already been made.

Paving work is still in progress.