Current progress of our project in Mońki

19, 01, 2018

Despite the adverse weather conditions, the construction is constantly moving forward.

The building A is at the lock-up stage and now fit-out works are being performed in the leased rooms. A loading platform with a dock shelter has been installed in the loading dock of the Biedronka store and the exterior finishing works are almost completed.

The ongoing works include hardening of the surrounding external area: almost half of the parking lot area has been covered with paving stones and the external lighting has been installed.

All binding joists in the building B have been reinforced, the surface is prepared for the application of concrete floor mix. The embedded plates for the roof truss have been installed and we are currently in the process of installing the roof structure.

The materials on this website are protected under the Act of 4 February 1994 on copyright and related rights. It is forbidden to copy and distribute any information, photographs, graphics, banners, signs, texts etc. on this website under the threat of legal sanctions.