The progres state of the first stage construction works on the investment in Babice Nowe on ul. Warsaw

18, 09, 2018

Currently, the assembly of sites is taking place, i.e. glazing, which is at the final stage. Finishing works inside premises such as plastering and laying tiles have also started.

The first air handling units were installed. The progress in road works can be seen - the foundations for parking lots are being made. All finishing works are carried out according to the set date.

We are passing the first premises to all tenants for adaptation.

The 1st stage of the investment was commercialized in 100%. We would like also to inform you that the design works related to the second stage of the investment have been completed and we are waiting for a building permit.

The main tenants are Biedronka, CCC, Pepco, Rossmann, KiK, Martes Sport, Empik, Neonet, Smyk, a pharmacy and a delicatessen shop.

We are glad to announce that the second stage has been commercialized in 85%.